Shop Drawings: What They Are and How the Review Process Works

George Dellas
Last Updated:
November 23, 2026
Read Time:
10 minutes
Shop Drawings: What They Are and How the Review Process Works

The steel fabricator sends 40 sheets of erection drawings and connection details for Level 2. Your project engineer forwards them to the structural engineer, whose reviewer is out for a week. The beams that were supposed to ship on the 10th haven't been cut, and the erector's crane date is getting close.

‍

Shop drawings are detailed drawings prepared by a subcontractor or supplier that show exactly how a specific building component will be fabricated and installed. They turn the design intent in the construction drawings into the exact dimensions and connection details a shop can build from.

‍

On most commercial jobs, shop drawings move as submittals. The general contractor checks and stamps them before the architect or engineer looks at them against the design. Nothing gets fabricated until the package comes back approved.

‍

Most of the waiting happens between those desks, so this guide treats every shop drawing as a line in the log with a spec section and a named owner from day one.

‍

What are shop drawings?

‍

Shop drawings are fabrication-level drawings of one component or system, such as a steel connection or a curtain wall anchor. Usually the subcontractor or its fabricator draws them. On some packages a detailing firm does the drawing.

‍

AIA A201-2017 Section 3.12.1 defines shop drawings as material prepared specifically for the work by the contractor or someone in its supply chain, to show how a portion of the work will be built. The same document settles two points that matter in the field. Shop drawings are not contract documents (Section 3.12.4), so they can't change the plans and specs. And the architect reviews them only for conformance with the information given and the design concept in the contract documents (Section 4.2.7).

‍

A construction drawing shows a steel beam with its size and elevation. The shop drawing adds the bolt pattern and the weld callouts, so the fabricator can cut steel without guessing.

‍

A shop drawing is one type of construction submittal, next to product data and samples. Start with what a construction submittal is, and see how shop drawings differ from product data.

‍

Shop drawings vs. construction drawings vs. as-built drawings

‍

Each set answers a different question at a different point in the project.

‍

Drawing typeWho produces itWhenWhat it answersContract status
Construction drawingsArchitect and engineersDesign phase, before biddingWhat the building should beContract documents
Shop drawingsTrade contractors, fabricators and suppliersAfter award, before fabricationHow one component gets fabricated and installedNot contract documents; reviewed against the design concept
As-built drawingsContractor teamDuring construction and at closeoutWhat was actually built, including field changesProject record for the owner

‍

Read in order, the three sets follow one component from design to what was finally built. Design drawings and schematics sit on the design side of that line, and our guide to construction schematics covers how they evolve before shop drawings start.

‍

What shop drawings include

‍

A shop drawing package has two readers: the reviewer checking it against the contract documents, and the shop that builds from it. Packages missing one of these items tend to come back.

‍

  • A title block with the drawing and sheet numbers, the revision number and date, and who prepared it.
  • A revision history describing every change since the last submission.
  • Dimensions and tolerances the shop will actually hold.
  • Material specifications: grades, gauges, finishes and part numbers.
  • Connection details, including fasteners, welds and how the piece meets adjacent work.
  • Field-verify hold points on any dimension that has to be measured on site first.
  • The spec section and contract drawing references for every item shown.
  • A bill of materials for procurement.

‍

The spec section reference carries the most weight. The shop drawing gets read against the section it claims to satisfy, so a missing reference leaves nothing to check against.

‍

Common types of shop drawings

‍

Each trade sends shop drawings with its own content and sticking points.

‍

TradeWhat the shop drawings showWhere it gets tricky
Structural steelErection plans, connection details, bolt lists, weld calloutsConnections delegated to the fabricator
RebarFabrication details for the shop and placing drawings for the fieldCongestion at beam and column joints
MEPDuct, pipe and conduit routing, sleeves, penetrations, equipment padsClashes in shared ceiling space
MillworkPlans, elevations, sections, hardware and finish schedulesField-measured openings and finishes
Curtain wall and glazingMullion profiles, anchors, glass types, thermal breaksAir and water performance, deflection
Precast concretePanel dimensions, reinforcement, embeds, lifting pointsEmbed locations and connections to the structure

‍

MEP often fills a large share of the log, since each MEP trade runs its own packages through the same ceiling zone. For plumbing, our breakdown of CSI Division 22 lists the sections that typically call for shop drawings.

‍

Who creates shop drawings and who reviews them

‍

Subcontractors and their fabricators prepare shop drawings. On a steel package that's often the fabricator's detailer, and on casework the millwork shop.

‍

The general contractor (GC) goes first. It checks coordination with other trades and completeness, then stamps the package before it goes to the design team. Under A201-2017 Section 3.12.5, the architect can return a package the contractor hasn't marked as reviewed without acting on it.

‍

The architect or engineer of record then reviews for conformance with the design concept. They don't check means and methods or fabrication dimensions, and that boundary keeps responsibility for dimensions with whoever prepared the drawing. On some jobs the owner signs off too, usually when a package affects building systems.

‍

Shop drawings arrive after contract award and before fabrication, with the heaviest volume in the first months of the job, when every trade needs approvals to order material.

‍

How the shop drawing review process works

‍

A shop drawing submittal moves through a fixed sequence:

‍

  1. The subcontractor or fabricator prepares the package and sends it up.
  2. Your team checks it against the spec section and the adjacent trades, then stamps it.
  3. The stamped package goes to the architect or engineer of record.
  4. The design team reviews it against the design concept and returns a status.
  5. You send the result back down the chain.
  6. If the package needs changes, the sub revises it and the cycle starts again.

‍

Each pass through that loop is a review cycle, and the schedule decides when each one has to start. For the full submittal workflow, see how the construction submittal process works.

‍

The four review stamps

‍

The status on a returned shop drawing tells the sub whether material can be ordered.

‍

  • Approved, often worded "no exceptions taken": proceed with fabrication as submitted.
  • Approved as noted: proceed after applying the reviewer's markups. Resubmission usually isn't required.
  • Revise and resubmit: correct the flagged items and send the package around again before any fabrication.
  • Rejected: the package doesn't meet the contract documents and has to be redone.

‍

Wording varies by design firm. No status moves design responsibility from the contractor to the design team. Under A201-2017 Section 3.12.8, an approval doesn't cover a deviation the contractor didn't call out in writing.

‍

How long does shop drawing review take?

‍

Your contract sets it. If the design team holds a 14-day window, those 14 days belong in the schedule ahead of fabrication, and each resubmittal adds another window. Write the period into each subcontract, so a stalled package is something you can document.

‍

Shop drawings live in the submittal log

‍

On the project, each shop drawing package is one line in the submittal log, with its spec section and an owner. The line also carries a due date and the current revision number. That's why the work starts before anyone draws anything.

‍

At kickoff, the PM and the superintendent go through the spec book together and flag every section that requires shop drawings, starting with long-lead items like structural steel and curtain wall. Each shop drawing gets its own due date, tied to the schedule as a predecessor to fabrication.

‍

From there, the log keeps packages moving. Each line should show who holds the ball right now and which revision is current. When a package comes back revise and resubmit, the new revision goes on the same line, so the comments from the last round stay attached.

‍

If you still build the log by hand, our free submittal log template is a good start. For everything that travels with the shop drawings, see what goes into a submittal package.

‍

Common mistakes that send shop drawings back

‍

Watch for these:

‍

  • Skipping the contractor's stamp, so the architect returns the package unreviewed and the clock restarts.
  • Subs sending shop drawings straight to the design team.
  • Revision numbers that disagree between the title block and the transmittal, so nobody can tell which version is live.
  • Deviations buried in a drawing note instead of called out in the transmittal.
  • Drawings copied from the design set with no fabricator detail added.
  • Resubmittals that answer only some of the comments.
  • Fabricating before approval to save time, then scrapping material when the drawing comes back with changes.

‍

Several of these trace back to version control or to a shop drawing sitting with the wrong person.

‍

Best practices for managing shop drawings

‍

These habits keep shop drawing review moving from kickoff to the last superseded sheet.

‍

Build the submittal log at kickoff

‍

Before mobilization, flag every shop drawing requirement in the spec book and order the log by lead time.

‍

Write review windows into the contract

‍

"Reasonable time" invites disputes. Put a specific period in each subcontract and in the schedule.

‍

Flag every deviation in writing

‍

Any change from the contract documents goes in the transmittal, where the design team will see it.

‍

Keep one current set of drawings

‍

When a revision arrives, every superseded copy in the field has to go. Link RFIs and submittals to the drawing sheets they affect, so the crew sees open questions on the plan itself. Our guide to construction drawing software covers what that setup needs.

‍

Run a completeness check before routing

‍

Before a package leaves your desk, confirm the spec section and the revision number. Then check that your stamp and every required detail are on it.

‍

How SubmittalLink handles shop drawing submittals

‍

SubmittalLink (that's us) is submittal, RFI and drawing management software for local builders. SubmittalLink manages and routes shop drawings. Creating them still happens in the detailer's CAD or BIM tools, and we don't do BIM coordination.

‍

  • The log builds itself. AI reads your spec book and generates the submittal register, organized by CSI MasterFormat or your own sections, so shop drawing requirements are on the log from day one.
  • Steps match your job. Custom workflows take as many steps as you need. Ball-in-court tracking shows who owes the next action, and automated reminders nudge whoever holds it.
  • Resubmittals keep their history. Every revise and resubmit gets automatic version control, with the comment history carried forward to the new revision.
  • Architects work from their inbox. External reviewers respond straight from the email notification, without creating an account.
  • Drawings stay current. The drawing management module keeps every sheet under version control, and AI reads the sheet numbers and revision dates when you upload a set.

‍

Every plan includes unlimited users, so subs and outside reviewers aren't locked out by per-seat pricing. Plans start at $150/month for builders under $5M in annual volume. On a $48M residential project with 850+ submittals, James Doyle, Project Manager at Ace Construction, put it this way: "SubmittalLink let us run tighter projects without the overhead."

‍

Shop drawings FAQ

‍

Are shop drawings part of the contract documents?

‍

No, under standard AIA language. A201-2017 Section 3.12.4 says shop drawings are not contract documents, so they can't vary the plans and specs. The exact language of your contract governs.

‍

Who approves shop drawings?

‍

The GC checks and stamps them first. The architect or engineer of record then reviews them against the design concept and returns the status. On some jobs the owner also signs off.

‍

Can fabrication start before shop drawings are approved?

‍

Generally no. Under A201-2017 Section 3.12.7, work covered by a required submittal shouldn't proceed until it's approved, and fabricating early risks scrapped material if the drawing comes back with changes.

‍

Does an approved stamp make the architect liable?

‍

Usually not. The architect reviews only for conformance with the design concept, so the contractor stays responsible for dimensions and for any deviation not flagged in writing.

‍

What's the difference between shop drawings and submittals?

‍

A submittal is anything the contractor sends for approval before installing work, such as product data or samples. Shop drawings are the type that shows how a component will be fabricated and installed.

‍